OCCUPATION DATE: January 2018

OCCUPATION DATE:

 

January 2018

3,000

 

Students

100,000ft²

 

Extension

£31 Million

 

Investment

The Build

The Curzon Building was the second phase of Birmingham City University’s city centre campus in 2015. It houses business, English, law and social sciences students and provides a student support hub plus new library, teaching and IT space. Construction also saw the restoration of a Victorian pub, The Eagle and Ball, which offers a unique new home to the Students Union. The Eagle and Ball pub was built between 1840 and 1850 and was known as The Moby Dick when it closed in 2007.

The client appointed Willmott Dixon for the following reasons:

  • extensive university track-record
  • know-how for live environment working
  • social investment programme for community
  • local team with impeccable construction credentials

3,000

 

Students

£31 Million

 

Investment

100,000ft²

 

Extension

The Build

The Curzon Building was the second phase of Birmingham City University’s city centre campus in 2015. It houses business, English, law and social sciences students and provides a student support hub plus new library, teaching and IT space. Construction also saw the restoration of a Victorian pub, The Eagle and Ball, which offers a unique new home to the Students Union. The Eagle and Ball pub was built between 1840 and 1850 and was known as The Moby Dick when it closed in 2007.

The client appointed Willmott Dixon for the following reasons:

  • extensive university track-record
  • know-how for live environment working
  • social investment programme for community
  • local team with impeccable construction credentials

BCU PHASE 2a PROGRESS

Milestones to Completion

8 weeks installation period

800 tonnes Structural Steel

210nr  11m precast planks (6 tonne each)

Installation includes precast stairs + edge protection system

Milestone 1 groundwork’s completed.

Steel Frame Commenced 4th July 2016

Milestones to Completion

8 weeks installation period

800 tonnes Structural Steel

210nr  11m precast planks (6 tonne each)

Installation includes precast stairs + edge protection system

Milestone 1 groundwork’s completed.

Steel Frame Commenced 4th July 2016